Mission
Spacecraft 3 flew on LJ-5
[edit]
Disposition
Destroyed at Launch
[edit]
Details
Some of the changes between Capsule 5 and the contemporaneous specification capsule were called out in
- The landing-bag system was not incorporated
- The attitude stabilization and control system was not fully operational, but was installed and used water to simulate the control system fuel
- Certain components of the communications system not essential to the mission were omitted
[edit]
Instrument Panel
Pending any new information in the February 1961 Edition of SEDR-104 or the August 1961 Edition of SEDR-104, Figs IP-1, IP-2, and IP-3 represent the SEDR-104 diagrams for the main instrument panel, and the left and right consoles of capsule 3.
[edit]
Chronology
- 15 December 1959
- The December 1959 Edition of SEDR-104 is published containing this Spacecraft as a test capsule
- 29 July 1960
- Spacecraft 3 delivered to Langley Field for a noise and vibration test.
- 27 September 1960
- Spacecraft 3 Erected at the Wallops Island launch site for the Little Joe 5 (LJ-5) mission.
- 8 November 1960
- LJ-5 Launched
- 1 February 1961
- The February 1961 Edition of SEDR-104 is published presumably containing this Spacecraft.
- 1 August 1961
- The August 1961 Edition of SEDR-104 is published presumably containing this Spacecraft.